Extended aftercare for completed construction works
The soft landings framework is a joint initiative between BSRIA (Building Services Research and Information Association) and UBT (Usable Buildings Trust). It is an open-source framework intended to ‘…smooth the transition into use and to address problems that post-occupancy evaluations (POEs) show to be widespread’ (ref Useable Buildings Trust).
The government considers that soft landings sits alongside Building Information Modelling (BIM), as BIM feeds facility management systems and helps enable future alterations to completed buildings. As a result, it is thought that, in parallel to the roll out of BIM, the government may mandate a Government Soft Landings (GSL) handover protocol for central government projects by 2016.
Soft landings includes provisions for initial aftercare and extended aftercare services for three years after the completed development has been handed over to the occupants. A decision to require this aftercare should be made early during the development of the project so that the necessary services can be included in tender documents and appointment agreements.
The Initial aftercare period is intended to deal with immediate problems, help the occupants understand the development, and help facilities managers learn to operate it. It is a period of intensive aftercare that will typically last 4 to 6 weeks.
After this, the aftercare on site will reduce over a period of 3 years. During this extended aftercare, review meetings will continue to be held, newsletters issued, and walkabouts undertaken but they will become less frequent as time progresses.
In year 1, outstanding problems are identified and resolved, continued training provided and systems fine-tuned, with regular reviews of performance, and comparisons with design predictions.
In years 2 and 3, performance is reviewed less frequently.
Post occupancy surveys should be carried out during year 2, ideally by independent organisations. These do not happen sooner, as the building will not yet have gone through a full year of operation, and so surveys could not properly account for different seasons or patterns of usage. In addition, if they were carried out sooner, surveys might be pre-occupied with teething problems rather than the underlying performance of the development. A second survey may be undertaken in year 3 to obtain additional feedback about the long-term performance of the development.
During this period, the facilities management team should log energy usage, and prepare regular written reviews of performance. Any fine tuning or other changes should also be recorded. Data and other evidence obtained during this period can help inform decisions about future alterations to the development.
A lessons learned report might be prepared at end of year 3.
This process of extended aftercare not only helps to inform users and facilities managers, it also provides the opportunity for the project team to learn about problems that have been encountered, assess what steps might be taken to rectify them and consider how to avoid them on future projects.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- BIM and facilities management.
- BREEAM Aftercare support.
- Building information modelling.
- Building log book.
- Building owner's manual.
- Building users guide.
- Building performance metrics.
- Client commissioning.
- Defects liability period.
- Government construction strategy.
- Handover to client.
- Initial aftercare
- Lessons learned report.
- Medical Research Council Laboratory of Molecular Biology soft landings project.
- Migration strategy.
- Occupation of completed construction site.
- Post occupancy evaluation.
- Post project review.
- Performance in use.
- Snagging.
- Soft landings.
- Soft Landings for owners.
- Technical guide.
Featured articles and news
Future Homes Standard Essentials launched
Future Homes Hub launches new campaign to help the homebuilding sector prepare for the implementation of new building standards.
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
Planning reform: draft NPPF and industry responses.
Last chance to comment on proposed changes to the NPPF.
A Regency palace of colour and sensation. Book review.
Delayed, derailed and devalued
How the UK’s planning crisis is undermining British manufacturing.
How much does it cost to build a house?
A brief run down of key considerations from a London based practice.
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.
AI-Driven automation; reducing time, enhancing compliance
Sustainability; not just compliance but rethinking design, material selection, and the supply chains to support them.
Climate Resilience and Adaptation In the Built Environment
New CIOB Technical Information Sheet by Colin Booth, Professor of Smart and Sustainable Infrastructure.
Turning Enquiries into Profitable Construction Projects
Founder of Develop Coaching and author of Building Your Future; Greg Wilkes shares his insights.
IHBC Signpost: Poetry from concrete
Scotland’s fascinating historic concrete and brutalist architecture with the Engine Shed.
Demonstrating that apprenticeships work for business, people and Scotland’s economy.
Scottish parents prioritise construction and apprenticeships
CIOB data released for Scottish Apprenticeship Week shows construction as top potential career path.
From a Green to a White Paper and the proposal of a General Safety Requirement for construction products.
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherited assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.